Washington is investing in defense contractors to expand production, raising questions about governance, competition, risk and taxpayer returns.
Setting those figures side by side does not suggest misuse; the filing ties the proceeds to construction, and the company says it is executing more than US$3 billion of missile-capacity investment through 2030. The pairing matters because it captures an arrangement now spreading through the defense industrial base: shareholders keep receiving cash while the state supplies part of the capital for the capacity it wants. The tools behind that shift run from the old government-owned, contractor-operated (GOCO) plants to preferred equity, price floors, guaranteed offtake and cancellation-protected multiyear contracts; this analysis groups them as "GOCO 2.0," a working label rather than an official category. Those tools may solve the industry's capacity problem while creating a governance problem of comparable weight, because the state increasingly acts as customer, financier, regulator and shareholder of the same firm, and the rules for those roles have not caught up with the money.
The capacity problem has roots in decades of capital discipline, visible in the filings of the largest contractors. Between fiscal years 2020 and 2025, Lockheed Martin, RTX, General Dynamics, Northrop Grumman and L3Harris together returned about US$128 billion to shareholders through buybacks and dividends, against about US$41 billion of capital expenditure, roughly 3.1 to 1. The totals include commercial businesses and one-off deals and do not prove underinvestment, but they describe a sector that returned surplus cash rather than build for uncertain orders. President Donald Trump's Executive Order 14372 of January 7, 2026 called this a failure, stating that contractors had been "incentivized to prioritize investor returns over the Nation's warfighters" and ordering the Pentagon to identify underperforming firms that pair payouts with insufficient investment.
Chart 1: Share repurchases, dividends and capital expenditures of five US defense primes combined, fiscal years 2020–2025, from Form 10-K cash-flow statements.
Shareholder payouts are the visible symptom of a deeper commercial logic, best described as the peacetime demand cliff. A contractor weighing a new propellant line must set decades of fixed cost against orders that arrive one appropriation at a time and can shrink when a crisis fades. Commercially optimal capacity, sized to expected orders, is therefore smaller than strategically necessary capacity, sized to a war that may never come. The difference, surge capacity that sits partly idle in normal years, earns little by conventional measures while its value lies in deterrence and in replacing what a war consumes. The United States has met this mismatch before. During the Second World War, about US$15.9 billion of the US$20.3 billion spent on new plant capital was federally financed, according to research drawing on Civilian Production Administration records, largely because firms would not risk their own capital on plants with doubtful postwar value; many of those plants were government-owned and contractor-run.
The recent record shows that money alone does not close the surge gap quickly, which is why the structure of financing deserves as much attention as its size. The Army invested US$4.5 billion in 155-millimeter artillery production between February 2022 and September 2025, yet output in March 2026 was 36,000 rounds a month, 36 percent of the 100,000-round goal set for October 2025, according to a July 2026 evaluation by the DoD Office of Inspector General (OIG). It also found that a contractor-owned metal-parts facility on which the Army spent US$469 million had produced no part meeting specifications. Lockheed Martin delivered 620 Patriot Advanced Capability-3 Missile Segment Enhancement (PAC-3 MSE) interceptors in 2025, and its framework agreement with the Pentagon aims for about 2,000 a year, a rate the company expects to reach by the end of 2030.
Chart 2: Latest reported output of two surge programs as a percent of their official capacity targets.
Shortfalls of that size explain why governments on both sides of the Atlantic are reaching past procurement contracts into the capital structure of production, with tools that differ in who owns the asset, who bears the risk of idle capacity and what the state gets back. Table 1 compares the main mechanisms now in use.
Table 1: How sovereign capital mechanisms allocate ownership and risk
| Mechanism | Verified example | Who owns the asset | Who bears demand risk | State's financial claim |
|---|---|---|---|---|
| GOCO plant | Five Army ammunition plants: Iowa, Lake City, Radford, Holston, Scranton | Government | Government for the plant; operator for contract performance | None beyond the output |
| Government-furnished property | Federal Acquisition Regulation Part 45, an exception to the rule that contractors supply their own property | Government | Shared, by contract | Title to the asset |
| Capital grant | European Union (EU) Act in Support of Ammunition Production (ASAP), €500 million (US$548 million); European Defence Industry Programme (EDIP), €1.5 billion (US$1.64 billion); UK energetics grants up to £45 million (US$59 million) each | Contractor | Contractor, eased by demand signals | None |
| Multiyear framework with recovery terms | PAC-3 MSE seven-year framework; L3Harris cancellation fees designed to cover facilitization | Contractor | Shifted toward the government if the program changes | None; shared efficiency gains |
| Loans to governments | EU Security Action for Europe (SAFE), up to €150 billion (US$164.4 billion) for member states | Varies | Borrowing state | Repayment |
| Preferred stock, price floor and offtake | MP Materials: US$400 million preferred, US$110 per kilogram floor, ten-year magnet offtake | Contractor | Largely the government, through the floor and offtake | 7 percent payment-in-kind dividend, warrants, 30 percent of prices above the floor |
| Convertible preferred in a subsidiary | L3Harris Missile Solutions, US$1 billion | Contractor | Contractor, backed by multiyear contracts | Preference, conversion discount, warrants |
| Passive common equity | Intel, US$8.9 billion for 9.9 percent | Contractor | Contractor | Common shares voted with the board |
| Direct state shareholding | Germany's agreed purchase of 50 percent of KNDS; France holds the other 50 percent | Company | Company | Full shareholder rights |
Sources: Congressional Research Service; Federal Acquisition Regulation 45.102; European Commission, ASAP; European Commission, EDIP; European Commission, SAFE; UK Ministry of Defence; Department of War; L3Harris Form 10-Q; MP Materials Form 8-K; Intel; tagesschau. Dollar equivalents use European Central Bank reference rates for November 27, 2026 (US$1.0957 per euro; US$1.3121 per pound, derived).
The oldest of these tools still carries much of the load, a reminder that public ownership of factories is not new to the United States. Most of the military's conventional ammunition, propellants and explosives comes from the five Army plants, each governed by one contract to operate and maintain the facility and another to buy its output, according to the Congressional Research Service (CRS). Ownership and operation are cleanly separated, yet even this model has unfinished governance: the Government Accountability Office (GAO) found in 2022 that the Army's documents assigning responsibility for the plants were outdated, and the Army told GAO in May 2026 that it expected to finish updating them later this year.
What distinguishes the newer arrangements is that the government takes a financial claim on the company rather than title to a building. The L3Harris transaction is the clearest case. The Pentagon announced a letter of intent in January 2026 for a US$1 billion convertible preferred investment in the missile business, funded through the Industrial Base Analysis and Sustainment (IBAS) program and paired with plans for multiyear procurement agreements for solid rocket motors. L3Harris closed the deal in April and keeps more than 80 percent of the business. Table 2 summarizes what the company's securities filings disclose about the terms.
Table 2: What the Pentagon bought in L3Harris's missile business
| Term | As filed | Why it matters |
|---|---|---|
| Instrument | 10,000 redeemable Series A convertible preferred shares of Aerojet Rocketdyne Holdings at US$100,000 stated value each, US$1 billion in total, plus warrants | The claim sits on a subsidiary, not the listed parent |
| Return floor | Liquidation preference of face value plus 7 percent cumulative annual dividends, compounded quarterly; L3Harris accretes toward US$1,422 million by April 17, 2031 | Debt-like downside protection for the government |
| Initial public offering (IPO) route | Automatic conversion at a 20 percent discount to the IPO price if a qualified IPO occurs by December 31, 2027; stake expected below 10 percent | A fixed return paid in a variable number of shares; later value tracks the share price |
| Route without an IPO | If milestones are met, conversion at face value divided by 15 times 2026 earnings before interest, taxes, depreciation and amortization (EBITDA), or redemption from April 17, 2031; if missed, redemption at 110 percent of the preference | The milestones themselves are not disclosed |
| Warrants | Rights to 3 percent of the common stock, fully diluted, at 100, 110 and 120 percent of the IPO or pre-IPO reference price | Added upside for the government |
| Use of proceeds | Net US$973 million to fund development and construction of missile manufacturing capacity | Ring-fencing exists on paper; enforcement terms are not public |
| Governance rights | Not described in the filings reviewed; the investment agreement is not filed as an exhibit | The central information gap |
Sources: L3Harris Form 10-Q for the quarter ended October 2, 2026, Note B; L3Harris Form 8-K, April 23, 2026.
The public terms describe an instrument built to protect the government's downside, while the missing terms bear most directly on governance. The April filing refers to "customary representations, warranties, and covenants," and the quarterly report says either side may force redemption "under certain conditions," but neither of the filings reviewed describes board or observer seats, information rights, consent rights over dividends or asset sales, or the milestones that decide which payout route applies. Without the milestones, outsiders cannot tell whether the government's return depends on production outcomes it also shapes as the buyer; without the governance terms, they cannot judge the Pentagon's influence beyond its contracts. The IPO that would convert the stock has also slipped, after L3Harris moved its target from the second half of 2026 to mid-2027, citing valuations.
The appeal for contractors becomes clearer through return on invested capital (ROIC), which divides net operating profit after tax (NOPAT) by the capital a company has tied up:
An illustrative production line shows what happens when part of that capital moves to the government. Suppose it needs US$1 billion of plant and equipment , earns a 10 percent operating margin on US$1 billion of revenue and pays a 21 percent tax rate. NOPAT is 1,000×0.10×(1−0.21)=79, or US$79 million, and ROIC is 7.9 percent. If the government owns or furnishes a share of the capital, only the remainder stays in the contractor's denominator:
Contractor ROIC doubles, yet the line makes the same output with the same total capital, so the return on all of it stays at 79/1,000=7.9 percent. Even if the contractor gives up a 5 percent pre-tax capital-linked return on the government's share, NOPAT falls to 79−(1−0.21)×0.05×500≈59, or about US$59 million, and reported ROIC still rises to about 11.9 percent. The figures are illustrative, but the mechanism is general.
Chart 3: Illustrative model of contractor ROIC and return on the line's total capital as the government's share of capital rises.
Separating those effects clarifies what government capital does and does not change. Some improvement may be genuine if public money buys automation that lowers unit costs, but much of it is a transfer: the capital denominator moves to the taxpayer while most of the profit stays with the firm. Procurement rules partly anticipate this. The Federal Acquisition Regulation (FAR) states that "contractors are ordinarily required to furnish all property necessary to perform Government contracts" and allows government property only when it does "not substantially increase the Government's assumption of risk" (FAR 45.102). The Defense Federal Acquisition Regulation Supplement (DFARS) profit guidelines assign contractor-owned equipment a normal value of 17.5 percent of facilities capital employed and tell contracting officers to weigh terms, such as termination protection, that reduce a contractor's investment risk (DFARS 215.404-71-4). Government-owned assets thus lower the profit a contractor can claim on capital, the dashed line in Chart 3, without stopping its ratios from improving.
The same boundary runs through depreciation and capital spending, so comparisons between contractors mislead once ownership differs. Under the FAR, depreciation, rental or use charges are unallowable on property a contractor acquired from the government at no cost (FAR 31.205-11), so a plant running government-furnished equipment (GFE) reports lower depreciation and capital spending than a rival that bought its own machines. Two equally efficient firms can thus show different capital intensity, asset turnover and ROIC simply because one operates on the sovereign's balance sheet. L3Harris's accounting adds a twist. The company recorded a US$386 million "program investment" intangible asset because, its quarterly report says, the fair value of the investment exceeded the cash received, partly because it provides "the opportunity to substantially expand an existing commercial relationship." The asset is amortized as a reduction to revenue over 20 years. In its books, investor and customer have become one accounting item.
That convergence is the core difficulty with preferred equity in a sovereign's hands. For a private investor, a cumulative preference, a conversion discount and warrants are standard ways to secure downside protection and share in the upside. For the government, the same features create a financial interest in the valuation of a company whose revenue it largely determines. The conversion discount locks in a fixed premium at listing, but the shares and the warrants, struck at and above the IPO price, gain value only as earnings grow, and the no-IPO formula is pegged to 2026 earnings. Those earnings depend on orders such as the seven-year undefinitized awards of US$6.3 billion on the Terminal High Altitude Area Defense (THAAD) program and US$4.7 billion on PAC-3 MSE that the missile business booked in the third quarter. On every route, the government's financial position improves as the contractor's earnings rise, and those earnings rise with government orders.
None of this implies that any award has been influenced by the investment, and no evidence of that has emerged; the problem is structural. Federal procurement conflict-of-interest rules were written for contractors and officials, not for a department that owns securities in a bidder. The FAR's organizational conflict rules aim at "preventing the existence of conflicting roles that might bias a contractor's judgment" and "preventing unfair competitive advantage" (FAR 9.505), and they are silent about a buyer holding a liquidation preference in one supplier. At a March 2026 hearing, House Armed Services Committee Chairman Mike Rogers asked how the department handles "the possible market implications or distortion" of its stakes, and Under Secretary for Acquisition and Sustainment Michael Duffey replied, "We are not pursuing control." That answer covers the boardroom but not the source-selection room, where a rival must trust that a department with money in its competitor will judge bids neutrally.
Competitive effects can follow from that position even when every official behaves properly. A supplier with government-backed capacity, multiyear orders whose cancellation fees are "designed to cover facilitization charges" and a sovereign shareholder can bid larger volumes with less private capital at risk than a self-financed rival, which may entrench incumbents in thin markets such as rocket propulsion. The remedies are familiar from finance: separating the office that holds equity from those that award contracts, walling off what the investor side learns, and publishing terms. The Senate Armed Services Committee's version of the fiscal year 2027 National Defense Authorization Act (NDAA) moves that way, according to the committee's summary as reported: it would place equity authority in the Office of Strategic Capital (OSC), bar the industrial base fund from taking stakes, require a conflict-of-interest review before investing, cap single investments at US$500 million, and limit equity to critical minerals, materials, chemicals and batteries. The bill stalled after cloture on the motion to proceed failed 50 to 46 on July 14, and negotiators had released no compromise text as of late November 2026
Washington has used passivity elsewhere to blunt the governance concern, and its limits are instructive. In the Intel deal, the government paid US$8.9 billion for a 9.9 percent stake with "no Board representation or other governance or information rights" and agreed to vote with the board, Intel said. At MP Materials, the Pentagon agreed to vote its common shares with the board, with exceptions, while taking consent rights over certain sales, according to the company's filing. Passivity keeps the state out of the boardroom but leaves commercial terms untouched, and MP's are extensive: a ten-year floor of US$110 per kilogram for neodymium-praseodymium (NdPr) products, purchase of all magnets from a new facility, and offtake terms under which that facility is to generate at least US$140 million of EBITDA a year at full capacity. A silent shareholder can still be the decisive economic actor.
Europe has faced the same problem with different instruments. The EU's ASAP selected 31 projects for €500 million in grants, expected to bring total investment to about €1.4 billion (US$1.53 billion). The €1.5 billion EDIP made its first production awards in October 2026, €168.2 million (US$184 million) for energetic materials, and SAFE, which lends up to €150 billion to member states, had disbursed almost €13.5 billion (US$14.8 billion) by late October. Britain's grants toward a £1.5 billion (US$1.97 billion) munitions pledge require applicants to show they can attract private investment. Germany has gone furthest toward ownership, agreeing in principle in early November to buy the family owners' 50 percent of KNDS, maker of the Leopard 2 tank, to match France's half. The Bundeswehr is KNDS's largest customer; a finance ministry document cited in reporting said Berlin wanted to avoid being outvoted on key decisions.
State capitalism is the label critics reach for, but its fit depends on the instrument. The difference from nationalization is real: private managers run nearly every plant in Table 1, private shareholders keep control of most of the companies, and the state's stake is usually minority, contractual or temporary. Yet the tools are spreading beyond defense, to chips and critical minerals, and the most assertive, a convertible security in a prime contractor's subsidiary, sits where the state's purchasing power is greatest. The Senate committee's sector list points the other way; on its terms, an IBAS-funded stake in a missile business would appear not to qualify. A September 2026 legal analysis argued that the department has never publicly stated a legal basis for its equity purchases. Whether GOCO 2.0 becomes durable policy or a contested experiment is now a question for Congress.
Who pays when capacity sits idle separates these instruments most sharply. In a traditional GOCO plant, the taxpayer owns the building and carries idle capacity directly. Under the PAC-3 framework, Lockheed Martin's chief executive, Jim Taiclet, said industry would be "rateably reimbursed for any sort of non-absorbed, non-recurring expense" if Washington changed the program, and the Army's seven-year contract action, with a US$58.62 billion ceiling, obligated no funds at award. L3Harris says its cancellation fees may not cover all its costs, and the stalled 155-millimeter parts facility showed that when government-funded capacity fails, public budgets absorb the loss first. Upside is allocated less consistently: the L3Harris preferred compounds at 7 percent, MP Materials owes 30 percent of NdPr prices above the floor once its new magnet plant reaches full capacity, and a grant returns nothing. Duffey told lawmakers that with equity "there will be an exit and that funding will return to the taxpayer." That is true of the instrument, but nothing ensures the return covers the risk absorbed through floors and cancellation terms.
The strongest case for sovereign capital is that the alternatives proved too slow. Private capital priced the demand cliff correctly; firms that returned cash rather than build idle lines responded rationally to Washington's signals. A preferred stake can be better stewardship than a grant, because it can return money and gives officials a view into the business. Duffey argued that the L3Harris structure led the company to "put their own billions of dollars" against demand, and the company's US$3 billion expansion plan supports that claim of leverage. The PAC-3 framework explicitly aims at "reducing upfront government facilitization and capacity investments." On this view, governance friction is a cost to manage, not a reason to refuse the tool, and the wartime precedent shows the United States can run hybrid ownership at scale.
Much of that case holds, and it narrows the thesis rather than defeating it: the more directly the state enters a contractor's capital, the earlier safeguards must be built. Today, the sequence runs the other way. The L3Harris investment agreement is not public, its legal authority is disputed, the Senate committee's guardrails remain unresolved between the chambers, and the Army's governance documents for its ammunition plants remain unrevised four years after GAO flagged them. Capital is arriving faster than the rules that would let competitors, auditors and taxpayers verify how it is used.
A government that buys capacity signs a contract; a government that joins the capital structure of the company operating it holds a claim. The contract ends when the missiles are delivered, while the claim persists through every later competition, restructuring and listing, giving the buyer a stake in decisions it also makes as regulator and customer. Governments may need such claims to rebuild production that markets will not finance alone. If they hold them, the defense industrial base will be shaped by who owns the capital, who carries the cost of idle lines and who decides which contractor wins the next award, and those answers deserve to be written down as precisely as the terms of the preferred stock already are.